A US food plant with four gas-fired boilers, modelled at nameplate in Heattech Pulse. The two-pass condensing unit takes the flue gas from 187 °C to about 50 °C and the feedwater from 30 °C to 85 °C, and the fuel bill falls by roughly a tenth — recomputed every minute from the plant's own signals.
| Plant | Northline Foods — 4 boilers (UB-01, UB-02, UB-03, UB-04) |
|---|---|
| Location / grid | United States · America/Chicago · USD |
| Capacity | 18.6 t/h steam across 4 boilers · 13,910 kW installed |
| Fuel | LPG (propane/butane) · NCV 45.9 GJ/t · CO2 2.985 kg per kg fuel |
| Heat recovery unit | two-pass condensing economizer (DXL) |
| Operating hours | 8,000 h / year |
| Data | Simulated instrument signals on the plant model — 1-minute samples |
The 4 boilers together fire 932 kg of fuel an hour and leave the stack between 186.5 °C and 187.2 °C. The flue-gas dew point is 56.7 °C, so everything above it is heat the plant paid for and did not use. Feedwater arrives at 29.8 °C.
| Boiler | Load | Fuel | Flue in / out | Water in / out | HR | Saved |
|---|---|---|---|---|---|---|
| UB-01 | 85.8 % | 114 kg/h | 186.5 → 50.2 °C | 29.8 → 85.0 °C | 114 kW | 9.94 % |
| UB-02 | 70.8 % | 157 kg/h | 187.2 → 50.7 °C | 29.8 → 85.0 °C | 153 kW | 9.74 % |
| UB-03 | 64.7 % | 229 kg/h | 187.1 → 50.6 °C | 29.8 → 85.0 °C | 225 kW | 9.79 % |
| UB-04 | 83.4 % | 432 kg/h | 186.5 → 50.5 °C | 29.7 → 85.0 °C | 423 kW | 9.80 % |
The condensing stage sits after the boiler and before the stack: flue gas passes the tube bundle, water passes the other side, and the unit is controlled to keep the stack above its minimum while still condensing. Effectiveness at this load is 87.0 %, with the stack margin held at 5.2 °C above the dew point.
| Metric | Value | Note |
|---|---|---|
| Heat recovered, right now | 915 kW | flue side and water side balanced |
| Fuel not purchased | 101 kg/h · 9.80 % | share of the fuel bill |
| Condensate collected | 341 kg/h | counted, not estimated |
| Boiler efficiency | 80.4 % → 89.3 % (GCV) | before → after |
| Cost per tonne of steam | 69 → 62 USD | fuel + water |
| Fuel cost avoided | $98/h | at 1 USD/kg |
| Period | Fuel not purchased | Heat recovered | Money saved | CO2 |
|---|---|---|---|---|
| Since commissioning | 43.4 t | 485.4 MWh | $41.5k | 129.7 t |
| Per year (8,000 h) | 810 t | 7,319 MWh | $780.4k | 2,418 t |
Water saved is condensate actually collected: 191.1 m3 since commissioning. No carbon price is added unless stated — the CO2 column is physical avoided CO2 at 2.985 kg per kg of fuel.
IPMVP Option B in structure: a measurement boundary drawn around boiler and economizer, continuous measurement of fuel, flue temperature and water flow/temperature, and savings computed from the measured heat recovery rather than from a design curve. The instrument signals are simulated from the boiler nameplate and the heat-recovery unit datasheet, and every number on this page is recomputed live from those signals — no customer and no invoiced saving is claimed.