1. Space and structure
| Item | Requirement | Checked by |
| Stack / duct length | Enough straight run for the module + bypass | Survey |
| Service access | 1.2 m on the tube side, 0.8 m on the casing side | Survey |
| Load bearing | Module weight + water volume on structure or independent frame | Structural check |
| Bypass | Manual dampers both sides — boiler can run with the unit isolated | Design |
2. Piping and drainage
- Feedwater tie-in points before the deaerator, with isolation valves.
- CHR: condensate drain to sampling point then to feedwater tank or drain — client decides the destination.
- Drain line sloped, trapped, and sized for 129 kg/h worst case on a 6 MW unit.
- No condensate return into the stack: a flooded stack is a corrosion event, not a saving.
3. Electrical, network, data
Power
230/400 V, 50/60 Hz, dedicated circuit per module (controls + instruments).
Network
Ethernet to the plant gateway; outbound HTTPS only.
Gateway
Reads Modbus/4–20 mA tags; buffers locally when the link is down.
UPS
Gateway and network on UPS — a power cut must not lose a day of metering.
Cyber
No inbound ports on the plant network; device key per gateway, revocable.
4. Safety and shutdown
- Tie-in during a planned shutdown only: 2–4 days per boiler including commissioning.
- Hot-work and confined-space permits per site rules; the unit is isolated and locked out before any welding.
- Existing boiler safety devices are not modified. If the flue pressure drop threatens combustion stability,
the bypass is opened and commissioning stops.
5. Commissioning checklist
- Leak test on feedwater side; flue-side pressure drop measured at design flow.
- Thermocouples cross-checked against a reference probe.
- Condensate flow verified against a weighed sample.
- PULSE tags verified one by one against the physical instrument; screenshot filed in the handover pack.
- Baseline week recorded before the retrofit is declared live.
6. Client responsibilities
Access for survey and commissioning, fuel invoices for the baseline, a network point, and a named plant engineer
for sign-off. Everything else — design, module, instrumentation, gateway, commissioning — is ours.