Installation requirements

What the site must provide before a heat-recovery module can be tied in — the list our engineers check during the survey, so the shutdown is short and the second visit is unnecessary.

1. Space and structure

ItemRequirementChecked by
Stack / duct lengthEnough straight run for the module + bypassSurvey
Service access1.2 m on the tube side, 0.8 m on the casing sideSurvey
Load bearingModule weight + water volume on structure or independent frameStructural check
BypassManual dampers both sides — boiler can run with the unit isolatedDesign

2. Piping and drainage

3. Electrical, network, data

Power
230/400 V, 50/60 Hz, dedicated circuit per module (controls + instruments).
Network
Ethernet to the plant gateway; outbound HTTPS only.
Gateway
Reads Modbus/4–20 mA tags; buffers locally when the link is down.
UPS
Gateway and network on UPS — a power cut must not lose a day of metering.
Cyber
No inbound ports on the plant network; device key per gateway, revocable.

4. Safety and shutdown

5. Commissioning checklist

  1. Leak test on feedwater side; flue-side pressure drop measured at design flow.
  2. Thermocouples cross-checked against a reference probe.
  3. Condensate flow verified against a weighed sample.
  4. PULSE tags verified one by one against the physical instrument; screenshot filed in the handover pack.
  5. Baseline week recorded before the retrofit is declared live.

6. Client responsibilities

Access for survey and commissioning, fuel invoices for the baseline, a network point, and a named plant engineer for sign-off. Everything else — design, module, instrumentation, gateway, commissioning — is ours.